Finance
Budget vs actual: does spending above plan mean money was wasted?
No, not by itself. Spending above plan can mean more jobs, more cost on each job, or both. A budget for 100 jobs at $20 is $2,000. If you then spend $2,310 on 110 jobs at $21, ten extra jobs explain $200 and $1 more per job explains $110.
Keep three numbers apart. A budget is your plan. A forecast is what you expect now, given what you know on that date. Actual is the real figure: what happened. A higher total can mean you did more work, each job cost more, or both. So split the difference into those two parts before you judge it. Note the period, and the date of each forecast, so you know what you're comparing.
Try it with your own numbers
Example values
The number of jobs the original plan for the period assumed. With no budget, use the number you expected.
The planned cost of one job, or the cost you expected if you have no budget. The split below fits when the jobs are alike, as in the example.
The number of jobs you expected at the date of your latest forecast. With no forecast, enter the number from your plan.
The cost of one job you expected at that date. With no forecast, enter the cost from your plan.
The jobs the records show for the same period. With no records, count the jobs you finished.
The cost of one job in the same category, from invoices and records, or your best estimate if you have none. With no cost per job, divide the period's total by the jobs completed.
Your result
- Actual cost over your plan: $310. A minus sign means under it.
- Your plan for the period: $2,000.
- The latest forecast for the period, or your plan if you entered it instead: $2,640.
- The actual cost for the period: $2,310.
- Of the difference from your plan, the part from completing more or fewer jobs at the planned cost per job: $200.
- Part from a higher or lower cost per job, across the jobs actually completed: $110.
- Actual cost over the latest forecast, or over your plan if you entered no forecast: −$330. A minus sign means under it.
Your numbers stay in this browser. Nothing you type is sent or saved.
How to find out what really happened
Ask what the extra work was and why the cost per job moved. Did the job change, or what went into it? Your job records, receipts or supplier invoices can answer that. If things have changed, you can update the budget. Keep the old and new versions, with their dates and the reason. Updates take work, so make them when they help you decide something.
Method
Each total = jobs × cost per job. Budget:
100 × $20 = $2,000. Forecast: 120 × $22 = $2,640. Actual: 110 × $21 = $2,310.
Over the budget = actual − budget:
$2,310 − $2,000 = $310.
Part from more jobs = (actual jobs − budgeted jobs) × budgeted cost per job:
(110 − 100) × $20 = $200.
Part from a higher cost per job = (actual cost − budgeted cost) × actual jobs:
($21 − $20) × 110 = $110.
Under the forecast = forecast − actual:
$2,640 − $2,310 = $330.
Special cases:
- The split fits when jobs are alike. If your work doesn't come in jobs, use what you do count, such as orders or customers served.
- With no forecast, compare actual with the budget only.
The workshop spent $310 more. What changed?
Illustrative scenario. These are fictional inputs, not customer results.
Before June, Jo plans materials for 100 identical jobs at $20 each. On June 10, new information leads her to expect 120 jobs at $22. By June 30, her records show 110 jobs at $21.
| Version | Jobs | Materials per job | Total |
|---|---|---|---|
| Budget before June | 100 | $20 | $2,000 |
| Forecast on June 10 | 120 | $22 | $2,640 |
| Actual at June 30 | 110 | $21 | $2,310 |
She spent $310 more than the budget. Ten extra jobs at $20 explain $200, and the extra $1 on 110 jobs explains $110. She also spent $330 less than the June 10 forecast. Both are true, and being under the forecast doesn't cancel being over the budget. The example has no stock timing or tax effects.
What this does not show
- Whether money was wasted. The totals can't tell you if the materials were wasted, were better quality or went into work that earned enough.
- Cash or profit. These are the costs of one activity, not payment dates, sales or the profit of the whole business.
- That a small difference is harmless. You may choose a size of difference worth checking, but smaller ones can still matter.
First step
Look at one cost from last month. Write what you expected it to be and what it was, with the number of jobs behind each. Then split the difference into more jobs and a different cost per job.
Answer these to see what your answers show about this.
Can the people who make decisions read and interpret your numbers?
free
Sources
CPA Australia: Improving business performance, page 5 (opens in a new tab) The different purposes of budgets and forecasts, comparing actual results and looking again at your assumptions. The June numbers are our own example.
ACCA: All about budgeting, part 2 (opens in a new tab) Updating plans as assumptions change, and the work that takes. Keeping the dated versions is our own suggestion.